August 2025 - Status Update State Project No. 0110-0136 Major Intersection Improvements on Route 6 at North Main Street and Agney Avenue

The Connecticut Department of Transportation will be providing an informational

public presentation at 6:00pm on September 2, 2025 in the Town Hall of all the

downtown items added to the project. The project is anticipated to resume

construction Fall 2025 through Summer 2026.


State Project No. 0110-0136 includes improvements along Route 6 in the Town of

Plymouth between Prospect Street and Baldwin Park Lane. The purpose of the

project is to improve the operations at the intersections of Route 6 with South Main

Street, North Main Street and Agney Avenue. Construction began on the project in

spring 2022. During paving operations in fall 2023, it was discovered that the

original ground survey model used to develop the project design contained

inaccuracies. Construction of the major roadway work has been paused while the

survey is corrected, and the design reviewed and updated to ensure roadway,

driveway, and sidewalk grading are constructed correctly. During this time, the

Department of Transportation has also identified some potential improvements

that could be made, such as extending streetscaping and illumination through the

project limits.